This page is open for editing because it is part of the Incubator. Have something to add? Please register so you can contribute. Have an option you would like to share? Please click on the 'Talk' button to enter the dialogue. The TF Resource Volunteers appreciate your feedback and interest.

Go to the Project-level traffic forecasting topic page.

References

NCHRP Report 765 reviewed literature about variability in traffic volume (Average Daily Traffic, or ADT) data. Although there were disagreements between studies as to methodology and results, the following equation, expressing the consensus of these studies, should be used for highway projects.

$$CV=\frac { 1.5 }{ { V }_{ }^{ 0.27 } }$$

where CV is the coefficient of variation (or the ratio of standard error to the mean) and V is the ADT.


Figure: example with ADT=1,000 to 50,000

CoefficientOfVariation.PNG